What the Route 16 Bridge Replacement Means for Broadway in Revere

November 19, 2026

"This is a bridge, but it is the gateway to our city," Conservation Commission member Brian Averbach said in April, according to the Revere Journal, when the commission reviewed MassDOT's plans for the Andrew A. Casassa bridge. The bridge carries Route 16, Revere Beach Parkway, over Route 107, Broadway, near the Cronin Rink. It is due to be torn down and rebuilt on the same footprint.

Whether you drive under it every morning or catch a bus at Broadway and Page Street, the key fact is where the work happens. In MassDOT's design, nearly all of the multi-year job takes place up on the Parkway. Broadway closes only overnight, for the few jobs that can't be done any other way.

An early-1930s bridge that already needed emergency help

The bridge dates to the early 1930s, and MassDOT's staff summary says it was widened in 1958. It's named for Andrew A. Casassa, Revere's mayor from 1929 to 1934. The Revere Journal notes he was the first municipal executive of Italian descent in the Commonwealth.

If the winter of 2025 still sticks with you, here's why. The Revere Journal reported that emergency repairs began January 28, 2025, with Route 16 lane closures in place around the clock. The crews strengthened deteriorated steel truss members, and the repairs were planned in three phases. MassDOT's October presentation to its Board says those repairs were needed to avoid traffic restrictions on a "poor condition" bridge that is part of the National Highway System. The project engineer called it a structure "at the end of its service life" when he spoke to the Conservation Commission.

The full replacement is the permanent fix, and MassDOT has set up the work to keep both roads open.

Three stages, all on the Parkway

The plan in MassDOT's January 15, 2025 design hearing presentation has three stages of about a year each. In every stage, the work zone sits on part of Revere Beach Parkway while the rest of the road stays open.

Stage Where the work zone sits Revere Beach Parkway Broadway by day Ramps
Stage 1, about 1 year Westbound outside lane Two lanes each direction No impacts for any road user Access maintained
Stage 2, about 1 year Eastbound and westbound inside lanes Two lanes each direction No impacts for any road user Access maintained
Stage 3, about 1 year Eastbound outside lane Two lanes each direction No impacts for any road user Access maintained

The design commits to keeping two lanes in each direction on Revere Beach Parkway the whole time. In practice, the Parkway gets narrower but never closes, and the street underneath carries on as usual during the day. The Revere Journal's coverage adds that the final stage also includes work on Broadway beneath the bridge.

The nights Broadway does close

Broadway does close on some nights. The design sets aside a 9 p.m. to 5 a.m. window for periodic closures, tied to two jobs:

  1. Demolition of the old structure over the road.
  2. Beam placement for the new bridge, a simple-span steel stringer design with a reinforced concrete deck.

On those nights, Broadway traffic gets detoured. MassDOT's October Board presentation repeats the commitment that any needed closures and rerouting of Broadway traffic "will occur at night only." If you work late shifts or count on Broadway for overnight trips, those are the dates to watch for once closure notices go out. MassDOT's project page for project 612184 is the official place that tracks the project.

Your bus keeps its daytime route

Since Broadway is planned to stay open by day, the buses that use it don't need daytime detours under this design. Two routes matter here:

  • Route 116 serves the Broadway @ Page St stop. If you still think of it as the 116 or the 117, the MBTA combined the two into Route 116 in December 2024 and discontinued the 117.
  • Route 110 offers crosstown service through Everett and Revere, running from Wellington to Wonderland via Broadway, according to the MBTA.

The early-morning bus lane stays part of the picture too. The design presentation lists the southbound Broadway bus lane, in effect from 4 to 9 a.m., as an MBTA transit priority project that's already complete. The bridge project is coordinated with it.

What Broadway looks like when the bridge is done

Broadway gets a lot of attention in this project for a road that isn't supposed to close by day. The scope includes Broadway itself, from the Revere/Chelsea line to the Taft Street intersection. According to MassDOT's design and the Revere Journal's coverage, the finished work includes:

  • Reconstructed sidewalks along that stretch of Broadway.
  • Bicycle accommodations on Broadway only, not on the Parkway, according to the Revere Journal.
  • Bus priority measures where feasible.
  • Upgraded signals at the eastbound ramp where it meets Broadway. That intersection stays signalized. The westbound ramp intersection stays stop-controlled.
  • ADA-compliant curb ramps and crossings at both ramp intersections.
  • More vertical clearance under the new bridge, with an aesthetic treatment that keeps its historic character.
  • An acceleration lane on the Parkway, made from what's now the westbound shoulder.

The slope by the bridge is part of the plan as well. Commission member Joseph LaValle asked about the big trees there. The Revere Journal reported he was told only one tree would come down and three new ones would be planted. The brush on the slope, which Averbach said traps trash, will be cleared and replaced with loam and grass.

Chelsea has its own plans for the stretch beyond the city line. The design presentation lists Chelsea's Broadway reconstruction, from City Hall Avenue to the Revere line, as having its final design submitted. It covers signal upgrades, a dedicated bike lane, and upgraded sidewalks and bus stops. If both projects go ahead, Broadway gets rebuilt on both sides of the line.

Where the contract stands

The project has been through public review for a while. MassDOT held a public information meeting on March 7, 2024, and a design public hearing on January 15, 2025. The Revere Conservation Commission voted unanimously at its April 1, 2026 meeting to approve MassDOT's notice of intent.

The bidding numbers are below.

Item Amount
Engineer's estimate $17,155,893.40
Low bid, MIG Corporation $17,867,504.50
Highest of six bids $25,969,872.20
Total budget with contingencies, engineering, police and other line items $20,998,531.68

The contract went out to bid on August 15, 2026, and bids were opened September 29. The low bid came in about $700,000 over the engineer's estimate, and the spread between the lowest and highest bids was more than $8 million. The project is funded with Next Generation Bridge Funds. MassDOT's Capital Programs Committee unanimously approved the contract on October 14. On October 21, MassDOT staff asked the full Board of Directors to authorize the award of Contract 136414 to MIG Corporation.

The contract allows up to 1,302 days from notice to proceed, which works out to about 3.6 years. In April, the Revere Journal reported that the start was set for 2027. Once work begins, the first year's work zone is the westbound outside lane on the Parkway, and Broadway stays open by day.

If you own a home near Broadway or Revere Beach Parkway and want to know how a multi-year project like this fits into your plans for selling or staying, The Caceda Team is happy to walk through it with you, at no cost and on your timeline. You can start with a free home valuation, or browse our Revere neighborhood page to see what else is happening around the city.